Introduction: Saudi Arabia's first sewage treatment PPP project—Dammam Independent Sewage Treatment Plant (Dammam ISTP)—2026 年 10 月 released its first-year operation results: cumulative sewage treated of nearly 5000 万 cubic meters, serving nearly 100 万 residents in western Dammam, equipment availability of 100%, and localization rate exceeding 50%. The competitive focus of the Middle East water market is shifting from "who can win the bid" to "who can keep assets continuously delivering data."
I. First Year of Operation: Four Data Sets Define the "Delivery" Standard
According to a review by China Water Network in early 11 月, the Dammam ISTP project was developed by a consortium comprising Metito Utilities, Mowah, and Orascom Construction. It is a flagship project of the national water strategy under Saudi Arabia's 2030 Vision and also Saudi Arabia's first sewage treatment PPP project. The first-year operation data released by 2026 年 10 月 show:
- Treatment capacity delivered—cumulative sewage treated in the first year of operation reached nearly 5000 万 cubic meters, equivalent to approximately 13.7 万 cubic meters per day, operating in the high-load range of the design capacity.
- Served population—covering nearly 100 万 residents in western Dammam, one of the most densely populated urban areas in Saudi Arabia's Eastern Province.
- Equipment availability of 100%—achieving full-year availability under the high-temperature, high-salinity, and high-sand coastal water quality conditions of the Gulf, reflecting the reliability of equipment selection and the O&M system.
- Localization rate exceeding 50%—directly responding to the localization requirements of Saudi Arabia's 2030 Vision, with local employment, local procurement, and local supply chain development all meeting the assessment thresholds.
The significance of these data lies in establishing a benchmark for "operational delivery" for PPP sewage projects in Gulf countries: in future tenders for similar projects, owners can directly cite the availability and localization rates of Dammam ISTP as qualification thresholds and performance baselines.
II. From Contract Signing to Performance Assessment: Two New Samples of the Gulf Sewage Market
Beyond Dammam ISTP, sewage treatment PPPs in the Gulf region are being rolled out at multiple locations. In 2026 年 1 月, the government of Ras Al Khaimah, UAE, signed the local first large-scale sewage treatment PPP agreement with a consortium comprising EtihadWE, TAQA Water Solutions, and France's Saur: initial treatment capacity of 6 万 cubic meters/day, adopting the Design, Build, Finance, Own, Operate, Maintain, and Transfer (DBFOMT) model, covering not only the sewage treatment plant but also pipe networks, pumping stations, and conveyance facilities, with plans to prioritize the use of treated sewage for irrigation and industrial purposes.
Viewed together, the two samples reveal a clear pattern: water procurement in Gulf countries is extending from "building a plant" to "managing an entire system"—contract scope includes pipe networks and pumping stations, performance assessment extends to the actual utilization of reclaimed water, and project value shifts from single facilities to full-lifecycle infrastructure management and water resource circulation. This forms a "stock operation + incremental PPP" dual-track pattern together with the LTOM long-term operation and maintenance program continuously advanced by Saudi Arabia's National Water Company (NWC) (within the year, tenders will also be launched for 51 plants of existing sewage treatment plants, approximately 88.8 万 cubic meters/day).
III. For Chinese Enterprises: Competitive Dimensions Are Being Rewritten
In the past, Chinese enterprises entering the Middle East water sector mainly relied on engineering contracting, equipment export, and large-scale infrastructure capabilities; contracts such as the Saudi NWC LTOM Package 10 (9 sewage treatment plants, 33.78 万 cubic meters/day, 15 年 cycle of approximately 23.66 亿 yuan) led and signed by United Water have advanced the role of Chinese enterprises from "equipment exporter" to "long-term operator." The first-year data of Dammam ISTP further demonstrate that winning the bid is only the starting point; long-term operational capability is the condition for survival.
For Chinese enterprises, this means at least three additional competitive evaluation dimensions:
- Long-term Operation and Risk Management Capability—A contract spanning 15 年 cycles tests a complete set of capabilities from facility renovation to sustained and stable operation, rather than the engineering management level during the delivery period.
- Localized Operation—A localization rate of over 50% has become a common requirement for Gulf projects. Local employment, local supply chains, and community relations development must be invested in upfront.
- Reclaimed Water Offtake Solutions—Contracts generally incorporate the use of treated sewage for irrigation and industrial purposes into performance metrics. Whoever can provide a solution under which reclaimed water can be "sold" will achieve better project economics.
IV. The "Chinese Share" in Global Water Treatment Equipment Procurement
Another figure worth noting: according to industry information cited by China Water Net, in global water treatment equipment procurement, the proportion held by Chinese suppliers is approximately 70%; relevant Saudi parties also plan to invest at least 150 亿 USD annually over the next three years to procure Chinese equipment, covering fields such as renewable energy, green hydrogen, and seawater desalination. The existing advantage on the equipment side provides a natural entry point for Chinese enterprises to upgrade from supply to operation—equipment is the beginning of "getting to know the owner," while operation is the way to "retain the owner."
Combined with Saudi Arabia's national plan to increase 2031 年 independent desalination capacity from 388 万 cubic meters/day to 718 万 cubic meters/day, as well as the demonstration effect of benchmark projects such as PowerChina's Rabigh Phase IV, the Middle East water sector is no longer an opportunistic market for Chinese enterprises, but a long-term strategic market requiring the formation of localized operation teams and the establishment of local joint venture platforms.
V. Key Points for Observation
- NWC's tender for 51 sewage treatment plants within the year—How the existing operation packages totaling approximately 88.8 万 cubic meters/day will be allocated will test the localized operation and organizational capabilities of Chinese consortiums.
- Dammam ISTP Phase II and similar PPP scheduling—Whether sewage PPPs in major urban areas such as Saudi Arabia's Eastern Province and Jeddah will replicate the "Metito model."
- Reclaimed water performance of the Ras Al Khaimah project—The actual proportion of irrigation and industrial reuse will become a leading indicator for water asset valuation under the DBFOMT model.
About TIANYI TECH: TIANYI LIMITED has long followed industry developments in sewage treatment, reclaimed water reuse, and water resource recycling, providing information, consulting, and technical exchange services to industry clients. This article is compiled based on public information for industry reference.
Sources: China Water Net (early to mid-2026-11), Environmental Protection Online; public information from Metito, Mowah, and Orascom Construction, and relevant announcements from Saudi NWC.
Industry News
2026-11-07