[Mainland China] Juancheng Reclaimed Water Utilization Project Completed: First Application of Skid-Mounted Packaged Equipment, Dual-Membrane Process at 16,000 tons/day, Built in 14 Months

Industry News
2026-11-08

Introduction: Published by China Membrane Industry Association 11 月 3 日: The Ecological Water Supplement, Wetland Operation and Reclaimed Water Utilization Project in Juancheng County, Shandong Province has been completed and put into operation, marking the first application of skid-mounted packaged equipment in the field of Reclaimed Water Reuse. The project has a designed daily water supply capacity of 1.6 万 tons and adopts the "Ultrafiltration + Reverse Osmosis" dual-membrane process to achieve quality-based water supply. From contract signing to commissioning, it took only about 14 months, with the plant building and core equipment all prefabricated in the factory.

I. The Birth of a "Building-Block" Style Water Plant

According to the project record published by China Membrane Industry Association, the Juancheng Reclaimed Water Utilization Project is the first implementation project of Luxin Environment's "Green Water Source" signature brand. Unlike the traditional wastewater plant process of "building the plant first, then installing equipment," the membrane modules, pump units, chemical dosing systems, control systems and other functional units of this project were all integrated, assembled and pre-commissioned inside the factory. After the packaged equipment arrived at the site, it was directly lifted into position, connected to pipelines and powered up.

The project timeline clearly demonstrates the efficiency of this construction paradigm: contract signed and landed on 2025 年 9 月, factory acceptance and shipment completed on 12 月, on-site installation and commissioning on 2026 年 1 月, deployment of the automatic control system, online monitoring and data acquisition platform completed on 6 月, household metering connections of water supply branch pipes completed according to the distribution of enterprises in the park on 8 月, and joint trial operation entered on 10 月 — from contract signing to commissioning in only about 14 months. At the project site, "there was no hustle and bustle of large-scale civil construction." The Reclaimed Water plant building, membrane treatment workshop, demineralized water tanks, chemical dosing room, etc. have all been completed, and core main equipment such as Ultrafiltration and Reverse Osmosis have all been installed in place.

II. Dual-Membrane Quality-Based Water Supply: One System, Three Water Qualities

The project has a designed daily water supply capacity of 1.6 万 tons and adopts the "Ultrafiltration + Reverse Osmosis" (UF+RO) dual-membrane process. The Ultrafiltration effluent can meet general miscellaneous use and ecological water supplement needs, while the Reverse Osmosis effluent reaches demineralized water grade, providing high-quality production water for enterprises in the Juancheng Chemical Industrial Park. Quality-based water supply makes "one source water, multiple products" possible, building a closed-loop water circulation system of "Reclaimed Water — Production Water — Wastewater Treatment — Reclaimed Water."

For chemical industrial parks, the business logic of this system is straightforward: enterprises in the park need demineralized water for production, which in the past was either self-built demineralized water stations or purchased externally. The Reclaimed Water plant uses the compliant tailwater from the wastewater treatment plant as source water, which is then deeply processed through the dual-membrane process before being supplied to enterprises. The source water is nearly zero-cost, the per-ton water price is competitive, and the investment payback model is clear.

III. Why Skid-Mounted Matters: Moving the Water Plant into the Factory

Skid-mounted packaged equipment is not a new concept and has long been applied in oilfields and emergency water supply, but its use for park-level Reclaimed Water Reuse is a first. Its value is concentrated in three aspects:

  • Compressed schedule — civil construction and equipment manufacturing proceed in parallel, significantly reducing on-site work. The 14-month contract-to-commissioning cycle is nearly half that of the traditional model, substantially lowering the time cost of enterprises "waiting for water" during park investment promotion.
  • Quality moved upstream — welding, anti-corrosion and pipeline pressure testing are completed in a controlled factory environment, leaving only module assembly and commissioning on site. Project quality is no longer at the mercy of field construction conditions.
  • Flexible capacity expansion — modular units can be added group by group as park water demand grows, avoiding "one-step" over-investment. This points to the same trend as the "Water Membrane Cube" prefabricated smart water plant by OriginWater reported in early 11 月 (with schedule and footprint reduced simultaneously by 80%).

In other words, water plant construction is shifting from a "construction-site paradigm" to a "manufacturing paradigm": standardized design, factory-made components, and on-site assembly. This is less a construction technology innovation than a restructuring of the product logic of the water treatment equipment manufacturing industry.

IV. Suitability for County-Level Park Markets

Juancheng is a county under the jurisdiction of Heze, Shandong, with a medium-sized chemical industrial park. Such county-level parks are precisely the best fit for skid-mounted solutions: small individual scale (ten-thousand-ton level), clear water quality requirements (enterprise production water), limited construction funds, and urgent schedule requirements. The fixed costs of the traditional EPC model spread over small projects offer low cost-effectiveness, whereas the scale effect of skid-mounted packaged equipment comes from factory batch production rather than on-site construction organization, so small projects can equally enjoy the manufacturing-side cost curve.

Recent cases show that "reclaimed water quality-based supply in industrial parks" is being rapidly replicated across county-level chemical industrial parks nationwide: the shared features of projects such as the Ningdong Energy Base salt separation and crystallization, the Hami Yiwu park, and Baiyin's "reclaimed water uphill" are that they all anchor on production water use by enterprises in the park, take the dual-membrane process or salt separation process as the core, and have a construction period of 14–24 months. The introduction of skid-mounted equipment will further lower the entry threshold for this market.

V. Key Observations

  • Operating data — The recovery rate of the dual-membrane system, power consumption per ton of water and chemical costs, and the disposal pathway for Reverse Osmosis / RO concentrate are key indicators for evaluating the economics of skid-mounted solutions, to be disclosed after formal operation.
  • Franchise operation and water pricing — The pricing mechanism for Reclaimed Water in the park and the terms of water supply agreements signed with enterprises will determine the financing feasibility of similar projects.
  • Equipment supplier landscape — Skid-mounted solutions shift competition from "construction qualifications" to "product reliability," and equipment manufacturers with membrane system integration capabilities benefit most directly.

About TIANYI TECH: TIANYI LIMITED has long tracked industry developments in wastewater treatment, Reclaimed Water Reuse, and water resource recycling, providing information, consulting, and technical exchange services to industry clients. This article is compiled based on public information for industry reference.

Source: China Membrane Industry Association, "Project Growth Record: Juancheng Reclaimed Water Utilization Project Completed" (2026-11-03); public industry materials.