11月4日, the Phase I project of the Jinjiang Sludge Disposal Center, located in Andong Park of the Jinjiang Economic Development Zone, has officially been put into operation. It is a key project of Fujian Province and the province's first comprehensive utilization sludge incineration disposal project. The total investment of the project is approximately 10亿 yuan, with a Phase I daily treatment capacity of 1200 tons (sludge 900 tons/day + general industrial solid waste 300 tons/day), and a long-term total design capacity of 1800 tons/day. It is the first among similar domestic sludge disposal projects to implement coal-fired power plant-level ultra-low emission standards, with incineration waste heat used for heating and power generation.
11月4日, the launch ceremony for the official operation of the Jinjiang Sludge Disposal Center was held. As a key project of Fujian Province, the center is the province's first comprehensive utilization sludge incineration disposal project. The commissioning of the project means that sludge from all wastewater treatment plants in Jinjiang has a stable and reliable local outlet, with the service scope covering the entire city of Jinjiang and extending to surrounding areas such as Shishi.
Project Overview: 1200 tons/day Phase I capacity, 1800 tons/day long-term
The total investment of the Jinjiang Sludge Disposal Center project is approximately 10亿 yuan, with a total land area of 29067 square meters. The Phase I treatment capacity is 1200 tons/day (including sludge 900 tons/day and general industrial solid waste 300 tons/day), and the total treatment capacity is 1800 tons/day. The project includes a comprehensive treatment workshop, a comprehensive building, a comprehensive water pump house, a gatehouse, wastewater treatment facilities, a fire water tank, and ancillary supporting facilities. Sludge undergoes fully enclosed operation throughout the entire process from unloading, incineration, flue gas purification to fly ash curing.
According to the project construction unit, Jinjiang Fangyuan Ecological Technology Co., Ltd., the project adopts a sludge drying plus incineration process, with waste heat supplied externally for heating and power generation: "Compared with steam generated from traditional fossil energy, our carbon emissions are only 20% of theirs." The waste heat generated by incineration is used for heating and waste heat power generation, turning sludge from a "governance burden" into a "resource increment."
Three Highlights: Ultra-Low Emissions, Vertical Layout, Industrial Synergy
- Emission standards benchmarked against coal-fired power plants — The project is the first among similar domestic sludge disposal projects to implement coal-fired power plant-level ultra-low emission standards, which are stricter than those for conventional waste-to-energy projects, with key control of dioxins, particulate matter, and nitrogen oxides, providing a stricter environmental baseline for addressing the "NIMBY effect" of sludge incineration facilities;
- Vertical stacked layout saves land — A compact and intensive advanced process layout is adopted, with the unloading hall and receiving pit located at the bottom, and incineration, purification, and turbine units arranged upward. Materials are connected by gravity and short-distance conveyance, greatly saving land resources under the same disposal scale. The comprehensive treatment workshop adopts a super-high steel structure system, with a maximum construction height of 40.5 meters, a maximum span of 36 meters for the roof truss beams, and a total weight of 650 tons;
- Synergy between municipal sludge and industrial solid waste — The project precisely aligns with Jinjiang's footwear and apparel industry, co-processing industrial solid waste such as scraps, opening up the resource recycling chain for industrial solid waste and supporting the green transformation of regional industries.
Why Sludge Incineration Is Timely for County-Level Implementation
The sludge outlet problem is the "last link" in the urban wastewater treatment system and also the most difficult one. With the investigation and repair of sewage pipe networks and the advancement of plant-network integration, national sludge generation continues to rise, landfill space is increasingly narrowing, and many places have explicitly banned direct sludge landfill. After the revision of the Regulations on Urban Drainage and Wastewater Treatment, requirements for sludge transfer manifests and sludge quality testing have been further strengthened, and the compliance disposal cost of sludge is becoming explicit.
The demonstration value of the Jinjiang project lies in three aspects: First, the economic viability of county-level self-built centralized incineration facilities has been verified — a sludge scale of 900 tons/day is sufficient to provide stable "fuel" for the drying and incineration line, and supporting waste heat power generation offsets operating costs; Second, solid waste synergy expands the disposal radius — after connecting general industrial solid waste (such as footwear and apparel scraps), both facility load rate and revenue sources increase, avoiding load fluctuations such as "no sludge to burn when sludge supply is interrupted, and insufficient capacity when solid waste increases"; Third, ultra-low emission standards reduce siting resistance — the project is located in Andong Park of the Economic Development Zone rather than a remote landfill site, close to industrial customers, shortening the transportation radius while resolving NIMBY conflicts with high standards. The project has been listed as a typical case of ecological governance in Fujian Province and has received competitive subsidy funds of 1800万 yuan for ecological governance.
Implications for the Industry
- Drying Incineration + Waste Heat Utilization — is becoming the mainstream technical route for centralized sludge disposal, with strong replicability in coastal counties facing land constraints;
- "Municipal Sludge + Industrial Solid Waste" Synergy — provides a dual stabilizer of load and revenue for incineration facilities; equipment selection must account for the combustion characteristics of both material types;
- Ultra-Low Emissions Becoming the New Threshold — emission standards for sludge incineration facilities are aligning with those for coal-fired power plants, and demand for flue gas purification equipment (deacidification, denitrification, activated carbon injection, baghouse dust removal) will scale up in tandem with tightening standards.
TIANYI TECH focuses on technical services and solutions in the water treatment field, continuously tracking technological advances and project implementation in the harmless disposal and resource utilization of sludge, and providing professional information references for industrial and municipal clients.
Source: Quanzhou Municipal People's Government Portal, Jinjiang Municipal People's Government Portal (published on 2026年11月6日). This article was compiled and written by TIANYI TECH for reference only.
Industry News
2026-11-09