The Shandong Provincial Department of Water Resources 11月2日 published an article disclosing that the Jinan Changqing District 2×66万 kW advanced coal-fired unit heating provincial major energy project explicitly designated reclaimed water as the primary production water source at the water resources assessment stage, with surface water only as emergency backup. The project includes a newly built 5万 m³/d reclaimed water pumping station and the laying of nearly 10 km of dedicated pressure water transmission pipelines to directly supply the power plant's circulating cooling system, consuming approximately 300万 m³ of urban reclaimed water annually, driving water resources management to shift from "supply based on demand" to "demand based on supply."
I. Writing "Reclaimed Water" into the Water Resources Assessment: A Key Institutional Leap
Power plants are typical large water consumers, with circulating cooling make-up water accounting for the bulk of coal-fired unit water use. In the past, the water source plans for newly built power plants basically followed the logic of "drawing surface water nearby, drilling deep wells when insufficient, and using reclaimed water as a supplement." The Jinan Changqing project completely reverses this order: reclaimed water is locked in as the primary production water source at the water resources assessment stage, surface water is retained only for emergency backup, and the gate on groundwater is shut tight.
The institutional significance of this step lies in the fact that water resources permits are a hard prerequisite for energy projects to materialize. Writing the feasibility of reclaimed water supply, water quality assurance, and the schedule of transmission and distribution works into the assessment as preconditions is equivalent to requiring that "reclaimed water supporting facilities be planned, constructed, and commissioned in sync with the main works." Whether a project is approved depends first on whether reclaimed water supply can keep up—reclaimed water has transformed from a policy initiative of "encouraged use" into an executable and veto-capable administrative licensing constraint.
The article offers a precise summary of this shift: water resources management is moving from "supply based on demand" to "demand based on supply." For high-water-consumption projects, from now on the first question is "how much compliant reclaimed water can this city's wastewater treatment plants give me," before discussing capacity planning.
II. The Engineering Economics of the "Wastewater Treatment Plant—Power Plant" Direct Supply System
Institutional design must ultimately be delivered through engineering. The direct supply system of the Changqing project consists of three parts:
- Water source end—relying on the stable compliant effluent of Jinan Quanxin Ecological Environmental Protection Technology Co., Ltd., with urban domestic sewage as raw water after advanced treatment to meet standards, ensuring the sustainability of water quantity and quality from the source;
- Transmission and distribution end—a newly built 5万 m³/d reclaimed water pumping station and the laying of nearly 10 km of dedicated pressure water transmission pipelines to directly supply the power plant's circulating cooling system, with Guyunhu Reservoir surface water designated as the emergency backup water source and no groundwater extraction under normal operating conditions;
- Control end—fully equipped with flow and water quality online monitoring facilities to monitor key indicators of reclaimed water supply in real time, establishing an emergency response mechanism for water quality anomalies, with all power plant wastewater and domestic sewage treated and recycled within the plant, with no external discharge.
Each year, approximately 300万 m³ of urban reclaimed water enters the power plant's cooling system outside the boilers, meaning an equivalent amount of fresh water resources is freed up for domestic and ecological uses; the power plant side gains a water source "insurance policy" unaffected by dry years and cuts in water withdrawal quotas. In water-scarce northern China, this account is worthwhile no matter how you calculate it.
III. Institutional Closed Loop: From Regulations to Agreements to Assessment
Many reclaimed water projects fail on "buildable but unmanageable." The institutional arrangements of Changqing in this regard are worth copying. The project is aligned with the "Jinan Water Conservation Regulations," building a management closed loop of "planning sets direction, assessment guards the gate, agreements clarify rights and responsibilities, supervision ensures safety":
- Agreements clarify rights and responsibilities—improving the reclaimed water supply agreement, with supply volume, water quality standards, pricing, and liability for breach written into the contract; the supply and demand parties are not in a "collaborative relationship" but a contractual one;
- O&M has an owner—incorporating the reclaimed water pipeline network into the unified layout of urban municipal infrastructure, implementing reclaimed water pipeline laying in sync with urban renewal and road construction, resolving the transmission shortfall of "water available but undeliverable";
- Water quality backstop—consolidating multi-party O&M and water quality control responsibilities, with monitoring data traceable and anomalies auditable; the precondition for the power plant to dare entrust its circulating cooling system to reclaimed water is precisely this quality control system.
IV. Replicability Assessment: Which Cities Are Suitable to Follow
The applicable conditions of the Changqing model are not demanding: a city with stable compliant wastewater treatment plant effluent + a transmission radius on the order of 10 km + the presence of high-water-consumption industrial users. Quite a few northern cities meet these three conditions. For reclaimed water operators and engineering enterprises, three market signals follow:
- Direct-supply projects will become a standard package type — integrated EPC demand for dedicated pump stations + pressure pipelines + online water quality monitoring will scale up as approvals for power and chemical projects tighten;
- Industrial reclaimed water pricing now has a reference framework — power plants are willing to pay more for water source reliability than for municipal miscellaneous use, and industrial direct supply will become the most profitable tier in the reclaimed water revenue structure;
- Water resources assessment consulting and reclaimed water supply and distribution schemes will become new entry points for professional services, and those who intervene at the early stage of a project will lock in subsequent engineering orders.
When "supply determines demand" was written into increasingly more provincial water resources management practices starting from Shandong, reclaimed water is no longer the downstream of sewage, but the upstream of industrial layout.
TIANYI TECH focuses on technical services and solutions in the water treatment field, continuously tracking industrial reclaimed water direct-supply projects, the evolution of the water resources assessment system, and the construction of the "wastewater treatment plant—industrial user" transmission and distribution system, providing reference for reclaimed water reuse system schemes to municipal and industrial clients.
Sources: Shandong Provincial Department of Water Resources, "Turning Waste into Treasure and Opening New Sources: Reclaimed Water Empowers the New Industrial Picture of Shan Shui Changqing" (2026年11月2日), and the "Jinan Water Conservation Regulations." This article was compiled and written by TIANYI TECH and is for reference only.
Industry News