[Mainland China] Xun County Urban and Rural Water Supply and Drainage Integration EPC Invitation for Bids at RMB 1.602 Billion: 429 Villages, 60,000 m³/day Reclaimed Water Plant, 104 Integrated Stations

Industry News
2026-11-13
The Henan Provincial Public Resource Trading Platform11月3日 has issued an announcement: the Xun County Urban and Rural Water Supply and Drainage Integration Project (EPC General Contracting) is open for bidding, with a total investment of 16.02亿 yuan, covering the entire Xun County area—7 townships and 4 sub-district offices, totaling 429 administrative villages. The construction content includes expanding the Huadian Water Supply Plant from 3万 cubic meters/day to 9万 cubic meters/day, and renovating approximately 4450 kilometers of pipeline network; building 6 new wastewater treatment plants and 104 MBR integrated wastewater stations; as well as 1 reclaimed water plants with a capacity of 6万 cubic meters/day and 37 kilometers of distribution pipelines.

This is the largest single order in the national water sector this week. The investment scale of 16.02亿 yuan is certainly eye-catching, but what is more worthy of industry study is its construction content structure—within a traditional "urban and rural water supply and drainage integration" framework, reclaimed water plants appear for the first time as a complete unit: a capacity of 6万 cubic meters/day, equipped with 37 kilometers of dedicated pipeline network.

Three Networks of One County

The scope disclosed in the announcement can be broken down into three networks.

The first is the water supply network: the Huadian Water Supply Plant is expanded from 3万 cubic meters/day to 9万 cubic meters/day, with approximately 4450 kilometers of pipeline network renovation, approximately 9万 sets of household connection facility upgrades, and approximately 5.58万 smart water meters. The keyword on the water supply side is "capacity expansion + metering improvement"—a plant of 9万 cubic meters/day paired with 5.58万 smart water meters means a shift from "supplying water" to "accounting for it clearly," which is a prerequisite for rural water supply tariff reform.

The second is the wastewater network: 6 new wastewater treatment plants, 104 MBR integrated wastewater stations, 4 lifting pump stations, approximately 240 kilometers of DN300–DN500 reinforced concrete pipes, approximately 1100 kilometers of DN200–DN300 double-wall corrugated pipes, 540 kilometers of DN110 UPVC drainage pipes, and approximately 2.22万 inspection wells. This set of figures exposes the true form of wastewater treatment in plain agricultural areas—extremely scattered sites and extremely long pipeline networks. 104 integrated stations distributed across 429 administrative villages means one station for every four or five villages on average—small in scale and scattered in distribution, which is the fundamental characteristic distinguishing rural wastewater from urban wastewater.

The third is the reclaimed water network: 1 new reclaimed water plants with a capacity of 6万 cubic meters/day and approximately 37 kilometers of distribution pipeline network. This part is the most worth pondering: the reclaimed water plant scale reaches 6万 cubic meters/day, equivalent to a considerable proportion of the total capacity of the new wastewater treatment plants, and is equipped with 37 kilometers of dedicated pipeline network—indicating that the users and transmission routes for reclaimed water were already defined at the project approval stage, rather than "building the plant first and finding users later."

Why Reclaimed Water Entered the County-Level Package

In the past, the standard configuration for county-level water supply and drainage integration projects was "water supply plant + wastewater treatment plant + pipeline network." Reclaimed water was usually approved separately as a standalone upgrading or resource recovery project several years after the wastewater treatment plant was built and put into operation. Xun County has included the reclaimed water plant in the same EPC package for three practical reasons.

First, funding structure. The project funding source is government special bonds plus county fiscal matching funds. Special bonds have requirements regarding project profitability, and reclaimed water has clear water fee revenue, which can improve the cash flow of the entire project package and increase the success rate of special bond applications. Packaging reclaimed water together with water supply and wastewater is essentially using revenue-generating units to balance public welfare units.

Second, engineering interfaces. The reclaimed water plant shares intake pump stations, power distribution, sludge treatment, central control, and other facilities with the wastewater treatment plant; building them simultaneously can save duplicate investment. If the 37 kilometers of pipeline network were to be laid after road renovation is completed, excavation costs would multiply. One excavation, multiple pipes in the same trench is the most practical way to save money in county-level projects.

Third, policy orientation. The newly revised Water Law has explicitly incorporated unconventional water sources such as reclaimed water into the unified allocation of water resources, and urban miscellaneous water use should prioritize reclaimed water. As a major grain-producing province and a key province for groundwater overexploitation governance, Henan faces persistent pressure to replace groundwater with reclaimed water at the county level. Writing reclaimed water into the construction content at the project approval stage is the most economical way to respond to this pressure.

104 Integrated Stations: Opportunities and Pitfalls of Equipment Scaling

The most easily overlooked—yet possibly the largest cost component—of the Xun County project is the 104 MBR integrated wastewater stations.

The advantages of integrated stations are fast construction, small footprint, and prefabrication; the disadvantages are small individual station scale, high unit cost, and dispersed operation and maintenance. With 104 stations scattered across 429 administrative villages, if operated and maintained in the traditional "staffing each station" manner, labor costs will quickly devour all the project's returns. Many county-level projects in the industry have already failed here: three years after completion, stations shut down one after another, ultimately becoming "sunbathing projects."

For the 104 stations to survive, three conditions are indispensable:

  • Standardized station types — consolidate into three to five standard models based on treatment scale, unify equipment brands and spare parts systems, and turn "one design per station" into "model selection and configuration";
  • Remote centralized O&M — the flow rate, liquid level, Dissolved Oxygen / DO, membrane pressure differential, and effluent quality of each station are uploaded to the county-level platform, with automatic alarms for anomalies and on-demand dispatch, raising the number of stations managed per person from single digits to dozens;
  • On-site resource recovery — the way out for rural sewage lies in "on-site reuse." Treated water is used for farmland irrigation, landscaping, and road cleaning, reducing discharge links and compliance pressure.

For equipment enterprises, this is an opportunity to trade volume for price: 104 stations mean centralized procurement of membrane modules, blowers, pumps, and control cabinets, and the per-station cost can drop significantly. But the premise is that products must be "remotely manageable" — equipment without data interfaces that cannot connect to the county-level platform will be excluded at the O&M bidding stage.

16亿 yuan relies on special bonds: the real test for EPC contractors

The announcement's requirements for bidders are: Municipal Public Works Construction General Contracting Grade I + Water Conservancy and Hydropower Engineering Construction General Contracting Grade II; the project chief responsible person must be a Grade I Constructor with a senior professional title and no projects under construction; Section I is EPC (survey + design + construction + procurement), with a construction period of 1095日 calendar days; Section II is full-process supervision.

This set of requirements points to a specific capability: being able to do both municipal and water conservancy works, design independently, manage a three-year construction period, and align with the funding rhythm of special bonds. A 16亿 yuan project undertaken by a single entity for survey, design, construction, and procurement means that money saved through design optimization and money overspent in construction both fall on the same company's books — this is both an incentive and a risk.

For small and medium-sized environmental enterprises, direct bidding is unrealistic, but the opportunity lies in subcontracting and equipment packages: the core process packages for 104 integrated stations and 6 sewage treatment plants, and the membrane systems and concentrated water treatment units of a 6万 cubic meters/day Reclaimed Water plant, are all specialized sections that can be undertaken independently. Entering by following the general contractor is the most realistic way to participate in this type of county-level large package.

The shape of the county-level market is taking form

Looking at Xun County together with several recent projects, the project form of county-level water affairs is already quite clear: one package per county, with water supply, sewage, Reclaimed Water, and smart metering done together, investment relying on special bonds, a three-year construction period, and a single EPC entity taking overall responsibility.

The impact of this form on the industry is two-way. On the one hand, the project threshold has been raised, and only general contractors with full-disciplinary capabilities can enter; on the other hand, the market for specialized subcontracting has actually become larger — the general contractor cannot possibly complete the equipment for 104 stations, the processes for 6 plants, and 37 kilometers of Reclaimed Water pipelines on its own; it must procure.

TIANYI TECH's technical positioning in the fields of wastewater treatment and Reclaimed Water Reuse happens to fall precisely in the specialized subcontracting layer of this type of project: membrane process packages for Reclaimed Water plants, standardized station types and remote O&M solutions for integrated stations, and county-level Reclaimed Water transmission and distribution design. In the era of county-level packaging, enterprises that can make a single technical unit "replicable, remotely manageable, and priceable" will survive more steadily than those chasing general contracting qualifications.


Source: Henan Provincial Public Resource Trading Platform, "Xun County Urban and Rural Water Supply and Drainage Integration Project (EPC General Contracting) Bidding Announcement" (2026年11月3日, tenderee Hebi Xingjun Urban Construction Co., Ltd.). This article was compiled by TIANYI TECH industry research and is for reference only.