The Phase I project of the Jinjiang Sludge Disposal Center was officially put into operation on 2026年11月4日, with a total investment of approximately 10亿 yuan, and is Fujian Province's first comprehensive utilization sludge incineration disposal project. The Phase I daily processing capacity is 1200 tons (sludge 900 tons/day, general industrial solid waste 300 tons/day), with a long-term total capacity of 1800 tons/day. The process is sludge drying plus incineration, with waste heat supplied externally for heating and power generation; the carbon emissions of the steam produced are only 20% of those of steam from traditional fossil energy; the project is the first among similar sludge disposal projects in China to implement coal-fired power plant-level ultra-low emission standards, which are stricter than those for conventional waste incineration power generation projects.
The significance of this news from Jinjiang lies not in "yet another sludge plant being put into operation," but in that it answers three long-pending questions at once: who provides the backstop for the sludge of a county-level city, according to what emission standards it is built, and on how much land it is built. With all three matters clarified, this type of project now has a template.
One plant covers an entire city: regional centralized disposal replaces "one sludge solution per plant"
Before the project was put into operation, the sludge outlet for all wastewater treatment plants in Jinjiang relied on off-site transport and decentralized disposal; during the rainy season, maintenance season, or when downstream receiving parties suspended operations, sludge accumulation was almost the norm. After the Jinjiang Sludge Disposal Center is put into operation, it will take over the sludge outlet for all wastewater treatment plants across Jinjiang, with its service scope extending to surrounding areas such as Shishi, and sludge will achieve fully enclosed operation throughout the entire process from unloading, incineration, flue gas purification to fly ash curing.
This means the logic of regional sludge governance has shifted: from "each wastewater treatment plant finding its own outlet" to "one centralized disposal center providing the backstop for the entire area." For local governments, this is the most controllable arrangement—a single but stable outlet, with scheduling authority in their own hands; for wastewater treatment plant operators, the compliance risks and price fluctuation risks of off-site sludge transport are stripped away at once, and the plant only needs to bring the moisture content to the design value. The cost of centralized disposal is the need for a sufficient collection radius and transport capacity, but for county-level economies like Jinjiang with a small area and dense plant and station distribution, the radius is entirely within a reasonable range.
Raising emission standards to coal-fired power plant level: the NIMBY threshold has been raised
The sentence in the project most worthy of industry peers' attention is: the first among similar sludge disposal projects in China to implement coal-fired power plant-level ultra-low emission standards. This is stricter than the conventional requirements for waste incineration, with key control of three items: dioxins, particulate matter, and nitrogen oxides.
Sludge incineration has long been stuck at "technically feasible, but not feasible in terms of siting." Public concerns focus on dioxins and odors, and previous industry standards could not provide a sufficiently convincing answer. Directly benchmarking emission limits against coal-fired power plant ultra-low emissions is equivalent to endorsing with a set of standards more familiar to the public and more maturely regulated. The chain reactions this brings are very practical:
- Flue gas purification shifts from ancillary to primary—to meet this standard, SNCR/SCR denitrification, activated carbon injection, and baghouse dust removal are almost mandatory combinations, and online monitoring must be networked with the ecological environment department; both investment and O&M costs must be put on the table at the feasibility study stage;
- Full enclosure becomes a hard constraint—the unloading hall, receiving pit, and comprehensive processing workshop are enclosed throughout the entire process; the reliability of the negative pressure collection and deodorization system directly determines whether stable operation can be achieved, rather than whether acceptance can be passed;
- Fly ash is incorporated into the closed loop—fly ash curing is set up as a separate step, indicating that the project has thought through the downstream destination of hazardous-waste-attribute materials from the design stage, which is not common among domestic sludge incineration projects.
2.9万 square meters housing 1200 tons/day: the vertical stacking land solution
The project land area is 29067 square meters, and Phase I alone must process 1200 tons/day. With conventional flat layout, functional areas are arranged in a line and pipelines are elongated, and the same scale often requires more than double the land. Jinjiang's approach is vertical stacking: the unloading hall and receiving pit are set at the bottom, and incineration, purification, and turbine units are arranged from bottom to top, with materials connected by gravity and short-distance conveying.
This layout places significantly higher demands on engineering capability. The comprehensive processing workshop adopts a super-high steel structure system, with a maximum construction height of 40.5 meters, and the roof truss beam with a maximum span of 36 meters and a total weight of 650 tons. In other words, the money saved on land is converted into money for structure and hoisting—in places like Jinjiang where industrial land quotas are tight and land prices are high, this trade is worthwhile; but in areas with ample land, flat layout may still be the more economical choice. There is no absolute superiority or inferiority in layout schemes; it depends on the intersection curve of land prices and structural costs.
From "disposal fees" to "energy and raw materials": the second leg of the business model
The project adopts sludge drying plus incineration, with waste heat supplied externally for heating and power generation. The operator's comparison is as follows: compared with steam generated from traditional fossil energy, the carbon emissions of this process are only 20% of those. At the same time, the project precisely aligns with the Jinjiang footwear and apparel industry and co-processes industrial solid waste such as scraps; the Phase I capacity of 300 tons/day of industrial solid waste is configured exactly for this purpose.
The combination of these two aspects means the project's revenue structure is no longer limited to the sludge disposal fee paid by the government: waste heat steam supply can be sold to nearby steam-using enterprises, waste heat power generation can be used on-site or fed to the grid, and industrial solid waste co-processing can generate disposal fees. Sludge has changed from a "governance burden" into a "resource increment" — essentially transforming a pure cost center into a facility with operating cash flow. This also explains why an investment of 10亿 yuan can be accepted at the county level — it is not just environmental protection expenditure, but also carries the attribute of industrial supporting facilities. The project has also received 1800万 yuan from Fujian Province's competitive subsidy funds for ecological governance, and has been listed as a typical case of ecological governance in Fujian Province.
For TIANYI TECH, the value of such projects lies in the way they twist together the three lines of sludge—energy—industrial solid waste. Our experience in sludge-water separation, dosing control, and odor removal accumulated in wastewater treatment and reclaimed water reuse systems is equally applicable to conditioning before sludge drying and to wastewater treatment within the plant; and the project's construction requirements of "fully enclosed process, all indicators online" also remind us: the competitive focus of future sludge projects is shifting from "whether it can be incinerated" to "whether it can be incinerated stably while meeting standards".
Sources: Quanzhou Municipal People's Government website, "The First in the Province! This Jinjiang Project Officially Put into Operation" (2026年11月6日); Jinjiang Municipal People's Government website, "Jinjiang Sludge Disposal Center Officially Put into Operation" (2026年11月6日); China Industry Economy Information Network, reposted from People's Daily Online (2026年11月). This article was compiled by TIANYI TECH industry research and is for reference only.