China Water Network (E20 Bidding Information System) 2026年11月9日 Announcement: The winning candidate announcement for the Changgang Comprehensive Water Quality Purification (Phase I) Project Construction in Hefei, Anhui (Evaluation-Determination Separation), with an estimated contract price of 114,052万 yuan, and the announcement period until 11月12日. The project includes a 20万 cubic meters/day Industrial Wastewater treatment plant, the Hefei No. 10 Water Treatment Plant wastewater discharge treatment facility of 1.8万 cubic meters/day, two sewage pumping stations, and off-site supporting pipe networks. Five groups of candidates — the China Construction Third Engineering Bureau consortium, Anhui Shuian, China Railway Fourth Bureau, the China Construction First Building Group consortium, and the CCCC First Harbor Engineering consortium — all submitted bid prices of 905,214,104.10元, identical to the cent, with construction periods all of 730天.
A 1.1 billion yuan project, and five bidders with central state-owned enterprise backgrounds quoted the same figure accurate to the jiao. This is not a coincidence, but rather the inevitable result of the game under the new "Evaluation-Determination Separation" bidding rules — understanding this string of identical numbers means understanding the changes in the competition rules for current large-scale water engineering tenders.
Why five bidders quoted the same number
The so-called Evaluation-Determination Separation is the separation of "bid evaluation" and "bid determination": the bid evaluation committee is only responsible for evaluation and ranking, while the right to determine the winning bidder is handed to the bid determination committee legally established by the tenderee. Under such rules, the commonly used competitive negotiation-style pricing strategy no longer works — because most Evaluation-Determination Separation projects adopt the "unified reasonable pricing method": the unified bid price is determined according to the prescribed downward floating rate, all bidders quote the same number, and price no longer constitutes a competitive variable.
Thus the game changes completely. Estimated price of 11.41亿 yuan, bidder price of 9.05亿 yuan, corresponding to a downward float of approximately 20.6% — this figure is uniformly prescribed by the tender documents, and all five candidates must accept it. Once the price is capped, what can each party compete on? Technical solutions, track record, credit, and the comprehensive assessment in the bid determination stage. This is exactly the effect the Evaluation-Determination Separation system design aims to achieve: bringing competition back from "who dares to undercut the price" to "who does the job well," and curbing the performance risks brought by malicious low-price winning.
The implication for bidders is direct: in Evaluation-Determination Separation projects, there is no room for maneuvering in the pricing stage, and resources should be fully invested in the technical bid and the bid determination presentation. The five candidates are announced in parallel, noted as "rankings in no particular order," indicating that the final attribution depends on the bid determination committee's selection of the best, which typically examines similar Industrial Wastewater track records, the proposed team, and local performance records.
20万 cubic meters/day: an Industrial Wastewater plant supporting an industrial cluster
The Changgang project itself is also worth a closer look. The Industrial Wastewater treatment scale of 20万 cubic meters/day is close to the main plant of a megacity; located in Hefei, it serves the industrial cluster of the Hefei Xinqiao Science and Technology Innovation Demonstration Zone. The project consists of four parts:
- Industrial Wastewater treatment plant 20万 m³/d — including wastewater treatment, sludge treatment, the front-of-plant area, and all auxiliary facilities within the plot; sludge treatment is built together with the main works, continuing the standard project configuration of "emphasizing both water and sludge";
- Hefei No. 10 Water Treatment Plant wastewater discharge treatment facility 1.8万 m³/d — the water purification plant's own sludge discharge water and backwash wastewater are also included in centralized treatment; this is a signal that the water supply plant's "Zero Liquid Discharge" has entered the scope of the wastewater general contract, and the design margin and recovery units for the plant's process water will become standard configurations for newly built water plants;
- 2 sewage pumping stations — No. 1 civil works scale 15万 m³/d, equipment installation 9万 m³/d; No. 2 civil works 10万 m³/d, equipment installation 6万 m³/d. The phased strategy of building civil works in one step and installing equipment as needed reserves flexibility for future water volume ramp-up, and is also a commonly adopted approach for current large-scale plants and stations;
- Off-site supporting pipe networks — the collection pipe network is tendered in the same package as the plant body, continuing the "plant-network integration" tendering trend and avoiding a situation where the plant is built without water or the pipe network lags behind.
A timetable for equipment and supporting suppliers
The 730天 construction period means the project will be completed around 2028年. According to the implementation pace of large wastewater plants, after the winning bidder is determined, the project will enter the detailed design and main equipment procurement stage within 3–6 months: main equipment packages such as blowers, pumps, screens, sludge scrapers, dewatering machines, chemical dosing systems, online instruments, and automatic control systems will be awarded successively. For equipment suppliers, the winning unit of this project should be locked in and contact established now — the period from the Evaluation-Determination Separation announcement to bid determination is usually only a few days, and the subcontracting and equipment inquiry windows after the contractor enters the site will not wait for anyone.
TIANYI TECH has mature products and engineering experience in the supporting systems for industrial wastewater treatment and reclaimed water reuse. Seeing an industrial wastewater treatment plant with a capacity of 20万 m³/day implemented in Hefei, what we focus on most is not who wins the construction contract, but the water use structure behind it: the ramp-up of water volume in the industrial cluster determines the phasing rhythm of wastewater treatment and reclaimed water reuse. The approach of completing civil works in one go and installing equipment in phases is precisely designed for the water use curve of the industrial park, where tenants move in and production capacity is reached gradually. The reclaimed water reuse unit (cooling make-up water, miscellaneous water) in such projects usually appears in the Phase II equipment package. We will keep tracking it, and we also remind peers to make phased bidding capability a prerequisite consideration in scheme design.
Source: China Water Network (E20 Environmental Platform Bid Information Collection System E-Biaotong) 2026年11月9日 winning candidate announcement information. This article was compiled by TIANYI TECH industry research and is for reference only.