[Mainland China] Kunming No. 15 Water Quality Purification Plant Passes Completion Acceptance: The Third Largest Fully Underground Facility in China, with Differentiated Treatment Capacity of 400,000 m³/day in the Dry Season and 600,000 m³/day in the Wet

Industry News
2026-11-18
Kunming Information Hub (Yunnan Daily) 2026年11月17日 reports: The construction project of Kunming No. 15 Water Quality Purification Plant has passed completion acceptance and entered the operational phase. The plant is the third largest fully underground water quality purification plant in China by treatment capacity and the fully underground wastewater treatment plant with the highest effluent standards in the country, with a dry-season treatment capacity of 40万 m³/day and a maximum rainy-season capacity of 60万 m³/day. It is the first wastewater treatment plant in China to feature differentiated treatment capacity for dry and rainy seasons while achieving the same effluent standard, and it implements Kunming's local Class A discharge standard, which is stricter than the national standard.

Once the rainy season arrives, a large number of wastewater treatment plants across the country face the same problem: inflow instantly doubles, and the portion exceeding treatment capacity can only overflow and be discharged directly. This large fully underground plant by Dianchi Lake in Kunming offered a new answer at completion acceptance — during the rainy season, the full volume is treated on site at 1.5 times the scale, and the effluent standard is not compromised. This design paradigm deserves serious study by all cities with combined sewer systems.

The Capstone Project of Dianchi Governance: Hard Strength in Numbers

Kunming No. 15 Water Quality Purification Plant is located on Baofeng Peninsula in Guandu District and is key infrastructure for the protection and governance of Dianchi Lake. Several key parameters illustrate its significance:

  • Both scale and standard are high — covering an area of 295.2 mu, with an underground floor area of 128416.74 m² and more than 1.7万 sets of equipment installed. It is the wastewater treatment plant with the largest treatment scale and the highest investment in Yunnan Province, and its effluent implements the Kunming local Class A standard, which is stricter than the national Class I-A standard;
  • Differentiated treatment for dry and rainy seasons — 40万 m³/day in the dry season and a maximum design flow of 60万 m³/day in the rainy season, with a total length of 10553 m of supporting off-site pipelines. It is the first wastewater treatment plant in China with differentiated treatment capacity for dry and rainy seasons while achieving the same effluent standard;
  • Rare process combination — the main process adopts an improved SBR biological tank + denitrification deep-bed sand filter + air flotation tank + deep-bed sand filter; sludge treatment adopts the "thickening + conditioning + plate-and-frame filter pressing" dewatering process, supported by dual disinfection with ultraviolet + sodium hypochlorite and a full-process combined odor control system;
  • Clear construction milestones — construction started in 2023年12月27日, the off-site pipe network was connected in 2025年11月30日, the main structure was topped out in 2025年12月19日, wastewater commissioning began in 2026年6月15日, and acceptance was passed after more than 5 months of joint commissioning and trial operation with stable compliance of effluent.

Why "Dry-Rainy Season Differentiation" Is a Paradigm Breakthrough

Traditional wastewater treatment plants have only two ways to cope with the rainy season: either build storage tanks to collect excess rainwater and treat it slowly, or discharge the overflow mixed water directly into rivers and lakes. The former has high land occupation and investment costs, while the latter pushes combined sewer overflow (CSO) pollution directly to receiving water bodies. The approach of Kunming No. 15 Plant is a third path: the rainy-season treatment scale is expanded to 1.5 times that of the dry season while maintaining the same effluent standard — excess rainwater is neither overflowed nor subject to lower standards, but treated clean on site.

For cities across the country with a high proportion of combined sewers, the replication value of this paradigm lies in: advancing "rainy-season overflow pollution control" from an engineering combination of storage + transfer to direct capacity expansion of in-plant process capability. The SBR process itself is a flexible framework for intermittent inflow, and combined with the advanced treatment chain of two-stage deep-bed sand filtration and air flotation, "design rainy-season flow" no longer means compromised effluent. New plants can be initiated directly according to this approach; existing plants undertaking rainy-season capacity expansion retrofits also have a design benchmark to refer to.

Fully Underground + High Standard: From "NIMBY" to "YIMBY"

This plant also incorporates all mainstream configurations of fully underground wastewater treatment plants: above-ground landscape and public space restoration, full-process combined odor control to prevent odor escape, and dual disinfection to ensure effluent safety. The treatment facilities with an underground floor area exceeding 12.8万 m² are hidden beneath the ground of Baofeng Peninsula, leaving the surface to the city. Dianchi is a sensitive plateau water body, and the Kunming local Class A standard is a stricter constraint tailored specifically for the Dianchi Lake basin — effluent indicators directly determine the pollution load entering the lake.

For equipment and engineering peers, the message conveyed by this plant is clear: the main equipment list for large underground plants has already been standardized — large SBR decanting and aeration systems, deep-bed filter water distribution and air distribution, high-efficiency air flotation, plate-and-frame filter pressing dewatering, combined odor control, and ultraviolet disinfection are all procurement categories that can be directly benchmarked. The civil construction cost and operating power consumption of fully underground plants are relatively high, and the subsequently disclosed cost-per-cubic-meter water data is worth tracking.

TIANYI TECH has served as a supporting supplier for wastewater treatment and reclaimed water reuse projects for many years, and well understands the challenge that rainy-season water quality fluctuations pose to operating plants—staying stable in the dry season is a basic skill; handling the load in the rainy season is the real capability. Kunming No. 15 Plant wrote "60万 cubic meters in the rainy season" into its design documents and passed acceptance, demonstrating that full treatment during the rainy season has moved from a slogan to engineering reality. We will continue to monitor the plant's power and chemical consumption data after operation, and also recommend that peers include deep-bed filters, air flotation and deodorization equipment in their key stocking priorities for large-plant projects.


Source: Kunming Information Hub, "Key Infrastructure for Dianchi Lake Protection and Governance: Kunming No. 15 Water Quality Purification Plant Passes Completion Acceptance" (Yunnan Daily, 2026年11月17日). This article was compiled by TIANYI TECH industry research and is for reference only.