[Mainland China] Qingdao Zhangcun River Water Quality Purification Plant Expansion Races Toward Year-End Water Commissioning: RMB 724 Million, 60,000 m³/day Expansion, Quasi-Class IV Effluent Used On-Site for River Replenishment and Reuse

Industry News
2026-11-14
Qingdao Daily 11月9日 reports: The Zhangcun River Water Quality Purification Plant Expansion Project, a key project of 2026年 in Qingdao, has completed the acceptance of the main civil works structure and has fully entered the equipment installation and process commissioning stage, sprinting toward water commissioning by the end of the year. The project has a total investment of 7.2422亿 yuan, expands the wastewater treatment capacity by 6万 cubic meters/day, and simultaneously implements upgrading and reconstruction of the original plant's 4万 cubic meters/day, with effluent reaching Quasi-Class IV of the Surface Water Standard, and the tailwater used as landscape water supplementation for the Zhangcun River and Reclaimed Water.

The Zhangcun River Water Quality Purification Plant is located in Laoshan District, west of the Qingyin Expressway and on the north bank of the Zhangcun River, covering an area of 2.2 hectares. It is the first fully underground wastewater treatment plant in Qingdao's urban area — Phase I was commissioned in 2018年, and for several years its tailwater has continuously served as landscape water supplementation for the Zhangcun River, an invisible contributor behind the river landscape of "babbling streams and flocks of fish and gulls." In 2025年, the project successfully entered the list of "Benchmarking Wastewater Treatment Green and Low-Carbon Benchmark Plants" of the National Development and Reform Commission and the Ministry of Housing and Urban-Rural Development. This expansion pushes this benchmark plant into its second stage of development.

"Expansion 6万 + Upgrading 4万" packaged implementation — why it is noteworthy

Expansion projects in most cities only cover new construction, with existing capacity upgrading tendered separately and scheduled separately. The Zhangcun River project places the new construction of 6万 cubic meters/day and the upgrading and reconstruction of the old plant's 4万 cubic meters/day in the same project package for synchronous implementation. The industry insight is direct: expansion and upgrading are essentially two matters on the same process drawing — the advanced treatment process adopted in the new construction section is precisely the part that the old plant upgrading needs to fill in; doing the two sections as one is more economical in design interfaces, construction organization, and commissioning arrangements.

More important is the choice of project timing. The old plant is still in operation, and the upgrading and reconstruction must be carried out under the condition of no water supply interruption — this is precisely the most difficult part of fully underground plant construction: underground wastewater treatment plants have narrow spaces and complex pipelines, and equipment installation and process commissioning require refined organization. The project owner, Qingdao Water Group Yishui Company, has reserved personnel in advance, worked backward from the water commissioning milestone, and managed the year-end water commissioning as a hard constraint. For similar existing plant renovation projects, this organizational experience of "renovating while operating" is itself an asset.

Quasi-Class IV effluent: a "river-as-reservoir" reuse pathway

The effluent standard after expansion is Quasi-Class IV of the Surface Water Standard, and the tailwater has two destinations: landscape water supplementation for the Zhangcun River and Reclaimed Water utilization. This design constitutes a pathway worth careful reading — treating the river channel as a storage reservoir for Reclaimed Water.

The traditional Reclaimed Water model requires building separate Reclaimed Water plants and transmission and distribution networks, with large investment and long cycles; the Zhangcun River approach is to make wastewater plant tailwater directly meet Quasi-Class IV standards, supplement the river channel, and then transmit and distribute naturally along the river, with downstream intake points drawing water as needed. In this way, the river channel is both an ecological space and a water transmission channel and storage pond, and the construction cost of the Reclaimed Water supply system is greatly reduced. The prerequisite is equally clear: the effluent must stably meet Quasi-Class IV, and no pollution can flow in along the way, which places higher demands on drainage management within the watershed — river channel reuse essentially turns "network integrity" into part of the reuse water quality.

This corroborates the Chifeng case in Inner Mongolia that we previously analyzed: Chifeng uses 275 kilometers of pipeline plus 7 pumping stations to deliver Reclaimed Water to the industrial park, relying on "dedicated network transmission"; Qingdao's Zhangcun River relies on "river channel transmission and distribution." The two pathways have no distinction of superiority or inferiority; the choice depends on user distribution — dedicated networks for concentrated users with high water quality requirements, and river channels for dispersed users mainly focused on ecological and municipal miscellaneous uses. The scaling of Reclaimed Water is indeed stuck at the "network" rather than the "plant", and this is being verified by the practice of more and more cities.

From completion to benchmark: an evolution sample of a fully underground plant

Another highlight of the Zhangcun River project is the iteration of the fully underground wastewater treatment plant. When Phase I was put into operation in 2018年, fully underground was still an exploratory solution; seven years later, with the expansion, the solution has evolved into a complete combination of "fully underground + Quasi-Class IV + landscape water supplementation + Reclaimed Water + green and low-carbon benchmark." For high-density urban areas, the accounting for the fully underground solution has become increasingly clear:

  • Intensive Land Use — The ground surface can serve as public spaces such as parks and sports facilities, significantly alleviating NIMBY concerns and preserving urban land value;
  • Tailwater as Ecology — Tailwater directly serves river landscape, forming a positive cycle between wastewater treatment facilities and urban water ecology;
  • Benchmark Alignment — The green and low-carbon benchmark plant lists issued by the National Development and Reform Commission and the Ministry of Housing and Urban-Rural Development make energy consumption, carbon emissions, and resource recovery indicators explicit. New projects are designed according to benchmark standards, while existing facilities are upgraded through benchmark alignment.

TIANYI TECH provides process design and equipment integration services in the fields of wastewater treatment plant capacity expansion and upgrading, and Reclaimed Water Reuse. The practice at Zhangcun River suggests that urban wastewater facilities are evolving from "single treatment units" into integrated water circulation hubs of "treatment—reuse—ecology." The design scheme must incorporate tailwater destination, river carrying capacity, and long-term users into the boundary conditions from the very beginning. For cities currently in the "15th Five-Year Plan" period, this hub-based fully underground plant + river reuse combination is likely to become the default answer for wastewater facility upgrading in water-scarce northern cities.


Source: Qingdao Daily/Toutiao "Full Steam Ahead: Sprinting Toward Year-End Water Commissioning — Zhangcun River Water Purification Plant Expansion Project Under Intensive Construction" (2026年11月9日), and public information from the National Development and Reform Commission and the Ministry of Housing and Urban-Rural Development "Benchmarking Wastewater Treatment Green and Low-Carbon Benchmark Plants" list. This article was compiled by TIANYI TECH industry research and is for reference only.